Profil:
PGE SAPGE GiEK estimates cost of agreement with trade unions at Dolna Odra power plant at PLN 250 million
PGE's mining and conventional energy unit GiEK has reached an agreement with the trade unions at the Dolna Odra Power Station, PGE said in a market filing. The total cost of the protection package is estimated at approximately PLN 250 million (EUR 58.9 mln).
As reported, an agreement has been reached that takes into account the demands of the social side and the principles of responsible energy transition pursued by PGE.
"The process of reducing employment at the power plant will be gradual, which means that part of the team will remain professionally active. At the same time, the decision to extend the operation of the Dolna Odra Power Station and the two-stage shutdown of coal-fired units by the end of August 2026 will ensure continuity of energy supply and energy security for the country," the statement said.
gaw/ ana/ nl/