Mirbud builder inks approx. PLN 279 mln deal with Poland's road authority

Listed builder Mirbud has signed a nearly PLN 279 million (EUR 65.4 mln) worth contract with the State Treasury - Poland's road authority GDDKiA for the design and construction of the Skaryszew bypass and the new DK9 country road to Ilza, GDDKiA announced in a press release.


According to GDDKiA, the Skaryszew bypass is one of nine investments in Masovian region that will be carried out as part of the program to build 100 bypasses.

The contract will be completed within 36 months of its conclusion. However, no later than 10 months after the conclusion of the contract, the contractor must apply for a decision on the permit for the implementation of the road investment.

All works are expected to be completed in the second quarter of 2029.

mbi/ ao/

© Copyright
Wszelkie materiały (w szczególności depesze agencyjne, zdjęcia, grafiki, filmy) zamieszczone w niniejszym Portalu PAP Biznes chronione są przepisami ustawy z dnia 4 lutego 1994 r. o prawie autorskim i prawach pokrewnych oraz ustawy z dnia 27 lipca 2001 r. o ochronie baz danych. Materiały te mogą być wykorzystywane wyłącznie na postawie stosownych umów licencyjnych. Jakiekolwiek ich wykorzystywanie przez użytkowników Portalu, poza przewidzianymi przez przepisy prawa wyjątkami, w szczególności dozwolonym użytkiem osobistym, bez ważnej umowy licencyjnej jest zabronione.

Waluty

Waluta Kurs Zmiana
1 CHF 4,5542 -0,16%
1 EUR 4,2586 -0,25%
1 GBP 4,8812 -0,04%
100 JPY 2,4630 0,28%
1 USD 3,6245 -0,19%